Thursday, October 23, 2014 Complete unit has been finished and installed within 17 weeks after signing the contract! Installation, start up and commissioning has been done within 3 weeks only! Capacaty: 600 m³ / day Modules: RCDT XXL 168 / 54 / M-HP36